CONVEYOR TAIL END FRAME & TAKE UP TROLLEY

This project involved the replacement of existing coal mine conveyor stringers, tail end frame & take up trolley. The existing structural members and mechanical components were severely corroded and beyond repair. Draftsite was engaged to visit the mine site, and site measure up the all structural and mechanical items that were to be replaced.

Draftsite created 3D models of the existing members and associated parts. Draftsite modified the model to suit Clients requirements as some of the items were now to be made in bolted sections to make the site install and future replacement / maintenance easier. Draftsite issued shop fabrication drawings and site plans for Client to review. The items were manufactured, and all the manufacture parts & assemblies were successfully installed during shut down.